Millersville borough set to mill and pave the following streets June 30 through July 3.*
- East Cottage Avenue – From North George Street to 100 feet past Herr Avenue
- Herr Avenue – From East Cottage Avenue to Circle Road
- Circle Road – From Herr Avenue to the end of the cul-de-sac
The roads are to be milled on June 30 and July 1, if necessary. Paving is set to take place July 2 through 3.
Throughout paving operations, roads will be closed, and no access is permitted on or off the designated streets between the hours of 6:00 a.m. through 7:00 p.m. The roads will remain open to local traffic with minor delays expected.
Circle Road and Herr Avenue residents will have access through the High School onto Model Avenue to North George Street while East Cottage Avenue is closed in both directions.
Please contact the Millersville Borough website or call 717-872-4645 if you have any questions.
*Dates are subject to change.