School board approves bids on high school renovation/construction project

The Penn Manor board of school directors voted 8-1 Jan. 22 to approve bids on the high school renovation and construction project.

The board approved construction bids totaling $82.7 million and the notice for contractors to proceed on the project, which will replace major portions of the school and renovate others.

New classroom, agricultural education and athletic wings will be built, along with a new auditorium and upgrades to the school’s HVAC, plumbing, electrical, fire suppression, technology and security systems.

The project also will include a new district office at the high school, which will open up space for classrooms at Manor Middle School, where the office is currently located.

Board members Ken Long, Nicki Nafziger, David Paitsel, Rich Frerichs, Joseph Fullerton, Donna Wert, Mitchell Sweigart and Chris Straub voted in favor of approving the bids. Carlton “Herk” Rintz voted against the measure.

Construction bids came in about $4.6 million higher than anticipated, but school district officials are confident the higher costs can be covered without an additional tax increase over the original, four-year funding plan.

Penn Manor will be able to cover the additional expenses by using more of its reserve funds than originally planned, said Chris Johnston, the district’s business manager. Penn Manor has set aside $9.6 million so far for the project and has borrowed $40 million to cover initial phases and plans to borrow another $40 million to complete the project.

Major construction is scheduled to begin in March, and the project should be completed by summer 2022. Here are the bids that were approved Jan. 22.