1


Penn Manor School District

Act 34 Presentation
for the
Fred S. Eshleman Elementary School
Renovations & Additions
  • Presented by
  • Gilbert Architects
  • March 6, 2002


2
Agenda/Introductions
  • Welcome and Opening Remarks
    • Mr. Donald Stewart, Substitute Superintendent
  • Hearing Duly Constituted
    • Mr. Donald Stewart, Substitute Superintendent
  • Introduction of the Project
    • Mr. Donald Stewart, Substitute Superintendent
    • Mr. Donald Anderson, Board Member
  • Proposed Building Project
    • Mrs. Danielle V. Hoffer, R.A.,  Studio Director
    • Mrs. Jennifer R. Lecher, Project Manager
  • Direct and Indirect Costs
    • Mr. Stephen B. Skrocki, Business Manager
  • Public Comments and Questions
    • Mr. Donald Stewart, Substitute Superintendent
  • Adjournment
3
Hearing Duly Constituted
  • Mr. Donald Stewart,
    • Substitute Superintendent
4
Introduction of the Project
  • Mr. Donald Stewart,
  • Substitute Superintendent


  • Mr. Donald Anderson,
  • Board Member



5
Proposed Building Project
  • Mrs. Danielle V. Hoffer, R.A.
    • Studio Director, Gilbert Architects


  • Mrs. Jennifer R. Lecher
    • Project Manager, Gilbert Architects
6
Background Information
  • Summary of District-Owned Buildings and Land
  • PlanCon
  • Facility Study
  • Options Considered


7
 
8
 
9
Background Information:

  • Planning for Construction (PlanCon)
  • Facility Study
    • Demographics
    • Facility Evaluations
    • Planning Options
10
Options Considered
11
Selected Option
  • Option 1
    • Renovate Ann Letort and Fred S. Eshleman Elementary Schools with additions to accommodate program.
      • Ann Letort renovations and additions are currently wrapping up.
12
Proposed Project Description
    • Site Considerations:
      • Storm water management
      • Adequate parking provisions for day and evening functions
      • Separation of parent/staff and school bus traffic
      • Bus loading and unloading
      • Play area facilities
      • Increased play fields
13
Proposed
Building Description
    • Physical Plant Improvements
      • New Roof with Insulation
      • New Windows
      • New Electrical System
      • New Geothermal Heating and Air Conditioning System
      • New Casework
      • New Finishes
      • Asbestos Abatement
      • Wired for Technology
14
Proposed Building Project
    • Program Upgrades
      • Administration office to be enlarged to provide sufficient area for Principal, support staff and nurse’s area
      • Guidance Room
      • One classroom to be designated for Reading, Speech, and Instructional Support
      • Small Group Instruction Rooms
      • Enlarged Library with support spaces
      • New Multipurpose Room to accommodate cafeteria and physical education use simultaneously
      • New kitchen and building storage areas
15
Fred S. Eshleman Elementary
 Site Plan
16
 
17
Fred S. Eshleman Elementary
Proposed Floor Plan
18
 
19
 
20
 
21
 
22
 
23
 
24
 
25
Indirect Costs
  • Insurance 6,000
  • Equipment 40,000
  • Utilities 20,000
  • Supplies $20,000
  • Total Indirect Costs $86,000


  • Based on the value of a collected mill currently providing $1,655,000, the Indirect Costs may result in a potential millage impact of 0.052 mills.
26
Public Comments
and Questions
  • Mr. Donald Stewart, Moderator
27